Agile Project Management (AgilePM) Practitioner 온라인 연습
최종 업데이트 시간: 2025년06월06일
당신은 온라인 연습 문제를 통해 APMG-International AgilePM Practitioner 시험지식에 대해 자신이 어떻게 알고 있는지 파악한 후 시험 참가 신청 여부를 결정할 수 있다.
시험을 100% 합격하고 시험 준비 시간을 35% 절약하기를 바라며 AgilePM Practitioner 덤프 (최신 실제 시험 문제)를 사용 선택하여 현재 최신 78개의 시험 문제와 답을 포함하십시오.
/ 4
Question No : 1
During Timebox A, the Local Planning Authority Officer was sometimes asked to attend the Daily Stand-up meeting as a temporary Specialist team member, to represent any Planning Authority issues.
Is this an appropriate application of Agile Project Management for this project?
정답:
Question No : 2
Answer the following questions about the tracking and control activities carried out within the project.
Decide whether each activity has been applied appropriately and select the response that supports your decision.
During Foundations, the key stakeholders had very different views about the content and prioritisation for the high-level requirements. As a result, the Project Manager
organized a Facilitated Workshop with the project team to discuss and agree the requirements.
Is this an appropriate application of Agile Project Management for this project?
정답:
Question No : 3
What action should the Project Manager take during the Close-Out of Timebox C?
정답:
Question No : 4
What action should the Project Manager take to plan the deployment activities?
정답:
Question No : 5
What action should the Project Manager take regarding the remaining windows?
정답:
Question No : 6
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
정답:
Question No : 7
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?
정답:
Question No : 8
HOTSPOT
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column 2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.
정답: Here are the DSDM Principles that would most help to reduce or mitigate the listed risks:
The ‘Hoy for Hoy Hall’ Action Group may cause delay to the project if they are not kept updated on
how the finished rooms are going to look.
G. Communicate continuously and clearly
Timber Tigers will ensure that the front rooms are finished and approved by the end of Timebox
A. E. Build incrementally from firm foundations
The Architecture Angels IT support team may require more detail up front in order to approve the initial design for the new online reservation system.
A. Focus on the business need
The morale of the Solution Development Team may be adversely affected if the external web design
specialist is not a team player.
C. Collaborate
Empowering the Solution Development Team to manage themselves on a day-to-day basis may result in the Project Manager losing sight of what activities are being carried out, by whom and when.
H. Demonstrate control
Question No : 9
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.
Which Agile principle MOST influences this course of action?
정답:
Question No : 10
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?
정답:
Question No : 11
A three-month timeframe has been specified to catch the seasonal sales window.
Which Agile principle MOST influences this course of action?
정답:
Question No : 12
Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not happen again.
Which Agile principle MOST influences this course of action?
정답:
Question No : 13
Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional
wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?
정답:
Question No : 14
HOTSPOT
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.
정답: Here are the appropriate options for each assertion and reason combination:
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
C. True (Assertion) False (Reason)
Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
The Procurement Manager is an appropriate representative of the end user of the solution.
B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
A. True (Assertion) True (Reason) AND the reason explains the assertion
Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
D. False (Assertion) True (Reason)
Rationale: While the Business Ambassador should ensure that business needs are analyzed, the 'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
A. True (Assertion) True (Reason) AND the reason explains the assertion
Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.
Question No : 15
How should the Project Manager assist the electricians to deliver the wiring?