시험덤프
매달, 우리는 1000명 이상의 사람들이 시험 준비를 잘하고 시험을 잘 통과할 수 있도록 도와줍니다.
  / AACE-PSP 덤프  / AACE-PSP 문제 연습

AACE AACE-PSP 시험

Planning & Scheduling Professional (PSP) Exam 온라인 연습

최종 업데이트 시간: 2024년05월09일,120문제.

당신은 온라인 연습 문제를 통해 AACE AACE-PSP 시험지식에 대해 자신이 어떻게 알고 있는지 파악한 후 시험 참가 신청 여부를 결정할 수 있다.

시험을 100% 합격하고 시험 준비 시간을 35% 절약하기를 바라며 AACE-PSP 덤프 (최신 실제 시험 문제)를 사용 선택하여 현재 최신 120개의 시험 문제와 답을 포함하십시오.

 / 3

Question No : 1


Which of the following phases does NOT describe the commonly accepted construction life cycle?

정답:

Question No : 2


Which statement is true?

정답:

Question No : 3


You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay.
Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

정답:

Question No : 4


Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

정답:

Question No : 5


If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

정답:

Question No : 6


In its simplest form, what is the main drawback of critical path method scheduling?

정답:

Question No : 7


The amount of time that an activity can be delayed from its early start date without delaying project completion is called

정답:

Question No : 8


Each of the following accurately describes total float in a schedule EXCEPT:

정답:

Question No : 9


In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

정답:

Question No : 10


All the following describe the critical path of a schedule EXCEPT:

정답:

Question No : 11


Project delays are best analyzed

정답:

Question No : 12


When resource leveling craft labor for a critical path schedule, the scheduler

정답:

Question No : 13


Resource planning must take all of the following into account except for

정답:

Question No : 14


Under which circumstance should one perform resource-leveling calculations?

정답:

Question No : 15


Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

정답:

 / 3
AACE